The email
- From
- Sean Whitfield, Program Director
- To
- Rachel Okafor, COO
- Date
- 17 Oct 2026
- Subject
- HLOR fortnightly update: GREEN
Hi Rachel,
Quick update on the Home Loan Origination Replatform for the fortnight to 17 Oct.
Status: Green (Green last period). The program remains on track for go-live. Build is 85% complete and engagement with Lendara is strong.
Highlights
- Credit decision rules signed off by the Chief Credit Officer (memo, 15 Oct).
- Performance test approach delivered.
Changes
- Minor re-sequencing of build and test activities to optimise vendor engagement. No impact to go-live.
- Lendara API specification now expected 28 Oct following productive working sessions. (Originally 30 Sep, then 14 Oct.)
- Performance testing to be completed within SIT to protect the timeline.
Key dates
| Milestone | Original | Now |
|---|---|---|
| Build complete | 2 Oct | 30 Oct |
| SIT start | 9 Oct | 6 Nov |
| Pilot with 3 broker groups | 30 Nov | 30 Nov |
| Go-live | 1 Feb 2027 | 1 Feb 2027 |
Open items
- Data migration test plan (Priyanka): due 10 Oct, in progress.
- Resourcing in the integration team remains tight. Delivery team exploring options.
- Lendara API: ongoing engagement with vendor, monitoring.
Benefits: No change. Re-keying savings of $2.4M a year from Jul 2027 on track. Broker conversion uplift (+3 points) on track.
Outcome measures: Time to conditional approval 6.4 days (was 6.5 at start, target 2.0). Re-keying 37% (was 38%, target 10%). We’re confident both targets will be met.
Decisions needed: Nil. New risks: None.
Cheers, Sean
The brief
Ask the Chief of Staff what Rachel should look at.
Dig in
The email says Green and on track. Its own dates say build and testing have slipped four weeks while the pilot and go-live haven’t moved, and the outcome measures have barely shifted.
What to look at
Squeezed middle Evidenced
“Build complete 2 Oct → 30 Oct… SIT start 9 Oct → 6 Nov… Go-live 1 Feb 2027 → 1 Feb 2027”
Four weeks lost, pilot unchanged. The time has to come from testing.
Ask Sean: “If build is four weeks late, where does the time come from to keep the 30 Nov pilot?”
Repeat slippage Evidenced
“Lendara API specification now expected 28 Oct following productive working sessions. (Originally 30 Sep, then 14 Oct.)”
Moved twice, described as productive, and the blocker isn’t named.
Ask Sean: “This has moved twice. What’s really stopping Lendara?”
Quiet quality change Evidenced
“Performance testing to be completed within SIT to protect the timeline.”
Testing cut to protect the date, with no decision recorded.
Ask Sean: “Who agreed to fold performance testing into SIT, and what did we give up?”
Outcome not moving Claim
“6.4 days (was 6.5 at start, target 2.0)… 37% (was 38%, target 10%). We’re confident both targets will be met.”
Confidence isn’t backed by anything in the email.
Ask Sean: “What has to happen for approval time to fall from 6.4 days to 2.0?”
What’s missing
- A sponsor and a benefit owner.
- A new date for the data migration test plan, a week overdue.
- Any ask: “Decisions needed: Nil” sits beside tight resourcing with no named owner.
What’s good
- Original and current dates sit side by side, so the slip is visible.
- Credit rules are signed off, with the memo cited.
Reply you could send
Hi Sean,
Thanks for the update, and for showing original and current dates side by side. Before I take this as Green, can you help me with three things by Wednesday?
1. With build and SIT four weeks later, where does the time come from to keep the 30 Nov pilot?
2. What’s really stopping the Lendara spec, and who agreed to fold performance testing into SIT?
3. When will the data migration test plan land, and what do you need from me on integration resourcing?
Happy to talk it through.
Rachel
Kate Morris